Customer
|
Name
|
Year
|
|
FGSZ Zrt.
|
Hungarian-Croation transit gas pipeline
|
2011
|
|
TVK-Nyrt.
|
Replacement of accounting measuring loops
|
2010
|
|
Vabeko Kft.
|
Százhalombatta DHE power plant gas transfer station. Process control construction design documents.
|
2010
|
|
FGSZ Zrt.
|
Maintenance of AUMA drives
|
2010
|
|
EON Zrt.
|
Gönyü, process control installation for oil supply system
|
2010
|
|
FGSZ Zrt.
|
Dunamenti Power Plant gas supply, process control implementation
|
2010
|
|
|
Production quality monitoring system of food industry plants at 15 locations
|
1995-2009
|
|
|
Implementation of gas measuring of over 100 big consumers (gas suppliers, power plants, industrial facilities)
|
1999-2009
|
|
|
Gas chromatography at 15 Hungarian and 20 Ukrainian locations.
|
2005-2009
|
|
KVV Zrt.
|
Algyő "0" point – Hungarian-Romanian border transmission pipeline facility, implementation of process control
|
2009
|
|
Olajterv Zrt.
|
Preparation of complete permit application design documents for Báta and Városföld stations
|
2009
|
|
Petrolszerviz Kft.
|
Placing in production oil wells marked Gomba-6-8
|
2009
|
|
Petrolszerviz Kft.
|
Placing in production Léta and Álmosd wells as part of the Létavértes field upgrade project
|
2009
|
|
FGSZ Zrt.
|
Revamp of FGSZ Zrt. process control systems
|
2008
|
|
KVV Zrt.
|
Realizing and commissioning process control works of stations (DN100 disjunctors)
|
2008
|
|
Vabeko Kft.
|
Realizing electric and instrumental works at Beregdaróc-Hajdúszoboszló pipeline scraper
|
2008
|
|
KVV Zrt.
|
Realizing control engineering control task for DN800 PN63 between Szbatta DHE-Perbál
|
2008
|
|
Vabeko Kft.
|
Realizing Algyő "0" point process control engineering tasks
|
2008
|
|
MOL Nyrt.
|
II. stage of extending measurements that have legal effect, on the Füzesgyarmat production unit site of MOL Nyrt KTD
|
2007
|
|
MOL Nyrt.
|
II. stage of extending measurements that have legal effect, on the West Hungarian production unit site of MOL Nyrt KTD
|
2007
|
|
MOL Nyrt.
|
II. stage of extending measurements that have legal effect, on the North Hungarian production unit site of MOL Nyrt KTD
|
2007
|
|
MOL Földgázszállító Zrt.
|
Gas quality measurement reconstruction 2007
|
2007
|
|
Olajterv Zrt.
|
Design and implementation of gas transmission pipeline
|
2007
|
|
MOL Földgázszállító Zrt.
|
Creating basic design for Beregdaróc compressor station machine replacement project
|
2007
|
|
MOL Földgázszállító Zrt.
|
Process control engineering reconstruction 2007
|
2007
|
|
MIHŐ Kft.
|
Installation of ultrasonic measuring loops on the site of the heat provider
|
2007
|
|
Emerson Process Management Kft.
|
Testing process control system technical transport of EON NYKCE
|
2006
|
|
GE Energy Services
|
Installation of control of K101-K104 GE Mark VI turbine at Beregdaróc compressor station
|
2006
|
|
MOL Nyrt.
|
Extending measurements with legal effect KEKT
|
2006
|
|
MOL Földgázszállító Zrt.
|
Gas quality measurement development for 2005
|
2005
|
|
MOL Földgázszállító Zrt.
|
Design and realization of creation of flow measurement at Pusztaederics FMB in 2005
|
2005
|
|
|
Measurements of potable and sewage water technologies with self-produced and Endress+Hauser instruments, BUSZESZ general engineering monitoring system.
|
2004-2007
|
|
TVK Automatika Kft.
|
TVK Rt. instrumental and process control engineering works
|
2004
|
|
Petrolszerviz Kft.
|
Implementing the process control engineering works at Tiszabezdéd LPG transfer and storage site
|
2004
|
|
Petrolszerviz Kft.
|
Software works of multifunctional logistic base process control system at Tiszabezdéd LPG transfer and storage site
|
2004
|
|
Taurus Carbonpack Kft.
|
Renewal works of electric controls of Taurus Carbonpack Kft. silos
|
2004
|
|
MAL Zrt.
|
Complex process control system of Inota aluminium smelters (test phase).
|
2004
|
|
Kunpetrol Kft.
|
Designing the creation of remote start-up for machines in Füzesgyarmat
|
2003
|
|
X-Prompt Kft.
|
Setup of platform surface for GET
|
2003
|
|
Olajterv Zrt.
|
Designing process control indoor instrumentation for Beregdaróc compressor station
|
2002
|
|
MOL Rt. Beruházás
|
Implementation for MOL Rt. Beregdaróc compressor station of the assembly and the commissioning of instrumentation and process control system, the editing of station control system applications, as subcontractor – in cooperation with Rolls-Royce Entronic
|
2002
|
|
MOL Rt. Földgázszállítás
|
Upgrading Városföld junction data gathering-controling unit
|
2002
|
|
MOL Rt. Földgázszállítás
|
I. stage of remote monitoring system
|
2002
|
|
MOL Rt. Társasági Szolg. Beruházás
|
Process control works for Hajduszoboszló compressor station
|
2001
|
|
MOL Rt. Társasági Szolg. Beruházás
|
Installation of two-way measurement, junction expansion, Városföld
|
2001
|
|
MOL Rt. Társasági Szolg. Beruházás
|
Measurement of validated heating gas flows at Hajduszoboszló compressor station
|
2001
|
|
Olajterv Zrt.
|
Designing the process control indoor instrumentation of Beregdaróc compressor station
|
2001
|
|
MOL Rt. EFL Logisztika Üzemfenntartás
|
Thermo cell fitting for axial compressor diffuser
|
2000
|
|
MOL Rt. Társ. Szolg. Beruházás
|
Realization of heating gas consumption reduction, station controller replacement CCC for Nemesbikk compressor packageunits
|
1999
|
|
MOL Rt. Társ. Szolg. Beruházás
|
Installation of Algyő gas turbine
|
1999
|
|
MOL Rt. KTÁ KFÜ
|
Building of individual heating gas measurement for gas turbines
|
1998
|
|
MOL Rt. Társ. Szolg. Beruházás
|
Designing of heating gas consumption reduction, station controller replacement CCC for Nemesbikk compressor packages
|
1998
|
|
Spectris Components Kft.
|
Designing, cabling of vibration measurement system for compressor stations
|
1998
|
|
MOL Rt. Társ. Szolgáltatá Beruházás
|
Reconstruction of Beregdaróc compressor station (MV measuring bridge)
|
1997
|
|
MOL Rt. KFÜ
|
Outdoor instrumentation for process control engineering
|
1997
|